据媒体报道,台积电熊本第二座晶圆厂计划于2028年12月启用,制程由原定的6/12nm升级为3nm,一期产能规划为每月6,000片晶圆。台积电熊本一、二厂合计资本开支估计超过230亿美元,高于2024年时的200亿美元估计;一期投资获日本政府补贴6,451.5亿日元(41亿美元),政府支持总额可能达到或超过最初获批的7,320亿日元。
AI 生成摘要 · 以原文为准
TSMC’s 2nd fab in Kumamoto will open in December, 2028 and use 3nm production technology instead of the 6/12nm nodes originally planned, media report, adding the new 3nm production plan calls for 6,000 wafer per month (wpm) for phase 1 capacity.
-TSMC’s total capex investment in Fabs 1 & 2 in Kumamoto is now seen over US$23 billion, up from a US$20B estimate from 2024.
-A Japan govt subsidy for the 1st phase of investment has been set at ¥645.15 billion yen (US$4.1B), while total government support could meet or exceed the original ¥732 billion approved by Tokyo.
-TSMC also modified the 1st fab production plan to focus solely on 22/28nm (drop 12/16nm) at 45,000 wpm output, from 55,000 originally. $TSM #semiconductors #Japan
来源:Dan Nystedt · x.com